Q-2, r. 17.1 - Regulation respecting the regulatory scheme applying to activities on the basis of their environmental impact

Full text
222. The establishment and extension of a storm water management system that does not depend on a combined sewer system are eligible for a declaration of compliance on the following conditions:
(1)  the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned;
(2)  the storm water drained by the system or extension does not come from a high-risk site;
(3)  if storm water is infiltrated into the soil, the bottom of the works used for infiltration is situated at least 1 m above bedrock level or above the seasonal peak groundwater level established on the basis of the oxidation-reduction level observed;
(4)  the water discharged cannot come into contact with a wetland not situated on a riverbank or lakeshore and in the littoral zone of a lake or a watercourse via surface runoff;
(5)  it is designed in compliance with the Design code of a storm water management system eligible for a declaration of compliance (chapter Q‑2, r. 9.01);
(6)  only storm water management works determined by the Design code of a storm water management system eligible for a declaration of compliance are used.
O.C. 871-2020, s. 222; I.N. 2021-11-01; O.C. 1461-2022, s. 30.
222. The establishment and extension of a storm water management system that does not depend on a combined sewer system are eligible for a declaration of compliance on the following conditions:
(1)  the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned;
(2)  the storm water drained by the system or extension does not come from a high-risk site;
(3)  if storm water is infiltrated into the soil, the bottom of the works used for infiltration is situated at least 1 m above bedrock level or above the seasonal peak groundwater level established on the basis of the oxidation-reduction level observed;
(4)  the water discharged cannot come into contact with a wetland via surface runoff;
(5)  it is designed in compliance with the Design code of a storm water management system eligible for a declaration of compliance (chapter Q‑2, r. 9.01);
(6)  only storm water management works determined by the Design code of a storm water management system eligible for a declaration of compliance are used.
O.C. 871-2020, s. 222; I.N. 2021-11-01.
222. The establishment and extension of a storm water management system that does not depend on a combined sewer system are eligible for a declaration of compliance on the following conditions:
(1)  the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned;
(2)  the storm water drained by the system or extension does not come from a high-risk site;
(3)  if storm water is infiltrated into the soil, the bottom of the works used for infiltration is situated at least 1 m above bedrock level and above the seasonal peak groundwater level established on the basis of the oxidation-reduction level observed;
(4)  the water discharged cannot come into contact with a wetland via surface runoff;
(5)  it is designed in compliance with the Design code of a storm water management system eligible for a declaration of compliance (chapter Q‑2, r. 9.01);
(6)  only storm water management works determined by the Design code of a storm water management system eligible for a declaration of compliance are used.
O.C. 871-2020, s. 222.
In force: 2020-12-31
222. The establishment and extension of a storm water management system that does not depend on a combined sewer system are eligible for a declaration of compliance on the following conditions:
(1)  the specifications for the work are prepared in accordance with the standard specification BNQ 1809-300 or at least meet the requirements of that specification for the work concerned;
(2)  the storm water drained by the system or extension does not come from a high-risk site;
(3)  if storm water is infiltrated into the soil, the bottom of the works used for infiltration is situated at least 1 m above bedrock level and above the seasonal peak groundwater level established on the basis of the oxidation-reduction level observed;
(4)  the water discharged cannot come into contact with a wetland via surface runoff;
(5)  it is designed in compliance with the Design code of a storm water management system eligible for a declaration of compliance (chapter Q‑2, r. 9.01);
(6)  only storm water management works determined by the Design code of a storm water management system eligible for a declaration of compliance are used.
O.C. 871-2020, s. 222.